Complete Response Letter, Feb 28, 2011

Please refer to your New Drug Application (NDA) dated and received on April 30, 2010, submitted under section 505(b) of the Federal Food, Drug, and Cosmetic Act for progesterone vaginal ring.
Complete Response Letter · Feb 28, 2011 · p. 2Open the letter at p. 2 ↗CRL_NDA201110_20110228:p1:s14
We also acknowledge receipt of your amendment dated February 18, 2011, which was not reviewed for this action.
Complete Response Letter · Feb 28, 2011 · p. 9Open the letter at p. 9 ↗CRL_NDA201110_20110228:p1:s18
The particle size distribution of progesterone is considered to be critical for the consistent release of progesterone.
Complete Response Letter · Feb 28, 2011Open the letter ↗CRL_NDA201110_20110228:p1:s27
To address this concern, we continue to recommend that you conduct, prior to approval of your product, a randomized, active-controlled clinical trial to evaluate the efficacy of your product in women 35-42 years of age.
Complete Response Letter · Feb 28, 2011 · p. 4Open the letter at p. 4 ↗CRL_NDA201110_20110228:p1:s44
The trial should be adequately powered to demonstrate sufficient retention of efficacy in the progesterone vaginal ring arm when compared to the active comparator.
Complete Response Letter · Feb 28, 2011 · p. 4Open the letter at p. 4 ↗CRL_NDA201110_20110228:p1:s45
Details of the trial should be agreed upon with the Agency prior to the conduct of the study.
Complete Response Letter · Feb 28, 2011 · p. 4Open the letter at p. 4 ↗CRL_NDA201110_20110228:p1:s46
Satisfactory resolution of these deficiencies is required before this application may be approved.
Complete Response Letter · Feb 28, 2011 · p. 11Open the letter at p. 11 ↗CRL_NDA201110_20110228:p2:s12
8. Provide English translations of current approved foreign labeling not previously submitted.
Complete Response Letter · Feb 28, 2011 · p. 5Open the letter at p. 5 ↗CRL_NDA201110_20110228:p2:s31
If you have any questions, call Karl Stiller, Regulatory Project Manager, at (301) 796-1993.
Complete Response Letter · Feb 28, 2011 · p. 13Open the letter at p. 13 ↗CRL_NDA201110_20110228:p3:s11